Upcoming Opportunity: TC7/19 & TC8/19 Waiari Trunkmains Construction

Tauranga City Council (TCC) intends to issue an ROI to the market mid to late January to pre-qualify a limited number of contractors for the above packages of work.

The Waiari Trunkmains from 376 No. 1 Rd, Te Puke to Poplar Lane Reservoir will be split up into two packages to better align with TCC's understanding of what the market would deem as more attractive. 

Part A Section 1

This package consists of the following:

  • Construction of an approximately 4 km long PE pipeline of between DN 900 and DN 710 primarily by HDD.
  • Construction of all associated valve chambers, installation of isolation, air, scour valves and associated pipe work.
  • Testing and Commissioning of the above
  • Communication duct design, supply and installation.
  • Possible construction of a walkway

Part A Section 2

This package consists of the following:

  • Construction of an approximately 9.4 km long PE pipeline of DN 710 by predominantly open cut.
  • Construction of all associated valve chambers, installation of isolation, air, scour valves and associated pipe work.
  • Construction of 2 no. pipe-jacked sleeves under the East Coast Main Truck railway.
  • Drilling of pipelines under drainage channels, roads and stream crossings.
  • Slip-lining of existing DN 300 and DN 375 AC Inlet/Outlet pipes to Poplar Lane Reservoir and ancillary works.
  • Testing and Commissioning of the above.
  • Communication duct design, supply and installation

There will be no restriction on the number of packages that any contractor can apply for (i.e. one package or both packages).

The ROI will require information on relevant skills, relevant experience and track record.

Posted: Jan 18, 2019,
Categories: Public Notice, Tenders,