Right now, our focus is on supporting your welfare and maintaining the essential services you rely on like water, sewage and transport. Some other services are disrupted though, and most public facilities are shut. Find out what's happening with our services, facilities, parks and venues: www.tauranga.govt.nz/covid19  |  For information on coronavirus: covid19.govt.nz  |  Stay safe and be kind to one another - kia kaha Tauranga.

Menu

Latest news

Durham Street project update - Friday, 30 August 2019

The Spring Street intersection will be fully open by Sunday night in readiness for Monday traffic. This means you will be able to drive from Cameron Road through to Grey Street on Spring Street. What an exciting milestone for the project. Pedestrians will be using the completed footpath in the intersection. 

Durham Street will be two-way traffic from Spring Street to the carpark building entrance. 

The second lane of the carpark building will be completed and open, as the temporary exit lane, on Sunday. This will allow for the third and final lane to be constructed.

Highlights from the past week:

  • Completed the small retaining wall on the north east corner of Spring Street intersection.  
  • Completed cobblestones and footpath asphalt on Spring Street intersection outside the carpark exit doorway.
  • Progressed cobblestone work on north east corner of Spring Street intersection.
  • Poured second section of parking bays on the east side of Durham Street.
  • Poured concrete footpath up to Folks Brewers.
  • Completed lane two of Carpark building entrance.
  • Completed all street light foundations.
  • Planted gardens up to the parking building entranceway. What a wonderful milestone for the project. We will provide more information on the planting next week.

Durham Street planting

Work happening next week includes: 

Spring Street and Durham Street intersections

  • Complete the footpath cobblestone work on the north eastern side intersection. 
  • Fully open the intersection and remove barriers.
  • Intersection complete!

Durham Street

  • Outside Carpark building.
    • Open lane two and use as exit lane for next month on Sunday. 
    • Open footpath from Spring Street to carpark building entrance.
    • Open roadway to two way traffic from Spring Street to carpark building entrance.
    • Close lane three, excavate and pour footpath to Trustpower entrance. 
    • Temporary detour for pedestrians from carpark building. Please take care.
  • Outside Trustpower and Beaurepaires
    • Complete cobblestones outside Trustpower. 
    • Current access from carpark building to Trustpower entrance will be closed to construct footpath. Please use detour.
  • From Beaurepaires to Elizabeth Street
    • Pouring concrete footpath from Folks Brewers to Elizabeth Street. This work will be done late afternoon to minimise disruption to businesses.
    • Continue preparing and laying concrete in the parking bays.  
    • Please note that accesses to businesses, from Aspire to Elizabeth Street, may vary during the next week as work progresses on the laying of concrete on the footpath through this area. Access may be from one direction only during this time. We will provide appropriate signage and use our traffic controllers to assist the public in accessing the businesses.

Durham Lane

  • Preparing base metal and laying asphalt surface.  

Please be advised that this newsletter update will conclude at the end of the Durham Street and Durham Lane upgrade in October 2019.

Please contact Keith Campbell, Fulton Hogan Stakeholder Manager, if you have any concerns or questions. 

Posted: Aug 30, 2019,