Right now, our focus is on supporting your welfare and maintaining the essential services you rely on like water, sewage and transport. Some other services are disrupted though, and most public facilities are shut. Find out what's happening with our services, facilities, parks and venues: www.tauranga.govt.nz/covid19  |  For information on coronavirus: covid19.govt.nz  |  Stay safe and be kind to one another - kia kaha Tauranga.

Menu

Latest news

Durham Street project update - Monday, 7 October 2019

Please find the latest project updates below.

Highlights from the past week:

  • Cobblestone work has progressed around the carpark building entranceway.
  • Exit lane from carpark building has been opened.
  • Installed cobblestones at the Elizabeth Street intersection.
  • We continue to wait for the concrete parking areas to cure before we complete the asphalt surfacing.
  • Concrete will be cured later this week.
  • More light poles have been installed.
  • Work on the garden planting is delayed as we wait for the seats to be manufactured and installed.
  • Trustpower garden beds have been backfilled.


Photo: View of Durham Street.

Work happening this week includes:

Durham Street

  • Outside of Trustpower
    • Partial planting of garden beds to begin outside of the Trustpower entrance.
    • Complete the instillation of cobblestones at Beaurepaires entrance.
  • From Beaurepaires to Elizabeth Street.
    • Asphalt surfacing to be completed this week.
    • Continue cobblestone work on make-up strip between footpath and buildings basestation. 
    • Lights to be installed.

Please contact Becky Cox, Fulton Hogan Stakeholder Manager, if you have any concerns or questions at 027 403 2598 or becky.cox@fultonhogan.com.

Posted: Oct 7, 2019,