Right now, our focus is on supporting your welfare and maintaining the essential services you rely on like water, sewage and transport. Some other services are disrupted though, and most public facilities are shut. Find out what's happening with our services, facilities, parks and venues: www.tauranga.govt.nz/covid19  |  For information on coronavirus: covid19.govt.nz  |  Stay safe and be kind to one another - kia kaha Tauranga.

Menu

Latest news

Welcome Bay Road – Road closure 13 October 2019

Te Puke Highway roundabout to Reid Road

Good news, with completion of the pipelaying works at the Eastern end of Welcome Bay Road, the area close to Te Puke Highway roundabout is close to being reopened to traffic. To reopen the road, we need to reseal it which means we will need to close the east end of Welcome Bay Road to traffic and pedestrians on Sunday 13 October, from 7am to 3pm. 

Traffic management will be in place from 4.30am, an alternative access route is possible via Kairua Road. 

This work is part of construction for the Waiāri Water Supply Scheme. Other aspects of construction are progressing, including:
•    The installation of pipeline and valves continues on Welcome Bay Road and Te Puke Highway.
•    Preparation of the water treatment plant site has started, which means additional truck movements from time to time. 
•    The Poplar Lane slip lane reopened earlier this week.



We want to extend an apology to anyone this road closure may affect. To have as little impact on traffic as possible, our contractors (HEB Construction) will be working Sunday and make every effort to get work completed early. 

Find more information about the Waiāri Water Supply Scheme at www.tauranga.govt.nz/waiari

Posted: Oct 11, 2019,
Categories: General, Road closures,