Inspection fee |
Inspection fees in excess of those allowed for in the original permit type. This may be due to the activity taking longer than anticipated, unfinished or unsatisfactory works, acting on complaints and any other costs incurred by Council related to the activity. Reinspection is required if reinstatement of works is not satisfactory or repairs are not undertaken within timeframe specified.
|
|
$212.00 |
Retrospective works |
In general these works create high risk to other Road Reserve users and infrastructure as no formal approval has been granted to undertake works. Corridor Access Request applied for after works commenced onsite without consent. Fee applied in addition to the permit type relevant to the activity of works.
|
|
Double the fee to be determined depending on permit type applied
|
Non-utility works |
In general these works create very low risk to Road Reserve Zone users and infrastructure. This permit type will include the cost of 1 site inspection for active or completed works. |
- Minor scaffolding works associated with small scale ‘renovation or building maintenance.
- Shop front fit outs / repairs / replacements.
- Crane operations.
- Building cleaning operations (water blasting).
- Annual Global Traffic Management plan (non-invasive works such as; surveying, sign replacement, i.e. billboards/shop frontages, inspections and kerbside collection activities).
- Road Reserve occupation i.e. skip bin, shipping/storage container
- Standard Vehicle Crossing installations (per IDC drawing T431) on Low Volume roads with minimal impact to traffic.
|
$191.00 |
Minor works |
In general these works create low risk to Road Reserve users and infrastructure. This permit type will include the cost of 1 site inspection for active works and 1 inspection for completed works.
|
- Up to 2 calendar days duration (excluding reinstatement).
- Simple service connections.
- Up to 20m affected length.
- Minor work associated with Utilities.
- Overhead veranda works/canopy replacement.
- Berm work only.
- Larger scale scaffolding projects occupying the Road Reserve.
- Annual Global Traffic Management Plan for low impact work in the berm only i.e. aboveground activities including vegetation control, garden maintenance and minor berm excavations of >50mm.
Note: multiple sites for Minor Works may be considered under a single application at the discretion of the Corridor Manager |
$329.00 |
Standard works |
In general these works create moderate risk to Road Reserve users and infrastructure. This permit type will include the cost of 2 site inspections for active works and 1 inspection for completed works.
|
- More than 2 and up to 30 calendar days duration.
- More than 20m and up to 250m affected length.
- Any road crossing or intrusion whether open trenched or trenchless.
- Moderate inspection requirement.
Note: multiple sites for Minor Works may be considered under a single application at the discretion of the Corridor Manager. |
$578.00 |
Comprehensive works |
In general these works create high risk to Road Reserve users and infrastructure.
This permit type will include the cost of 3 site inspections for active works and 1 inspection for completed works.
|
- More than 30 calendar days and up to a maximum of 12 months duration.
- More than 250m affected length.
- High inspection requirement.
- Major work on Level 2 Roads.
- Restricted property access.
- Annual Global Traffic Management Plan (Physical activity above and below ground).
- Construction sites (demolition & construction requires a separate application). |
$1,055.00 |
Maintenance works |
In general terms these are works agreed to by the Corridor Manager as likely to be completed under an Annual Global Traffic Management Plan (AGTMP). |
- Repair to an existing service or surface.
- Excludes new works within the Road Reserve.
- Can be completed with traffic management plans from an existing approved AGTMP i.e. if a site specific traffic management plan is required a separate permit fee may apply. |
No charge |
Emergency works |
An unexpected repair of a service to reduce the risk of significant or imminent threat of physical damage or destruction to Road Reserve users, infrastructure and property. |
- Duration no longer than 24 hours.
- Rectification of a dangerous situation including support requested by an emergency service |
No charge |
Not for profit' events and road reserve occupation |
Community events undertaken by any Charity or ‘not for profit’ organisation in the road reserve for any length of time. |
- Public activity or gathering, sporting event, show or parade |
No charge |