Building consent requirements
A building consent is not required to insulate an existing building, except for external walls and internal firewalls provided that the following is true:
- Building work in connection with the installation of thermal insulation in an existing building other than in:
- an external wall of the building; or
- an internal wall of the building that is a fire separation wall (also known as a firewall).
More information about building consents
Resource consent requirements
Many building projects may also require a resource consent. As part of the building consent process, applications are reviewed by a planner who can highlight any potential requirements, and provide some advice on what might be needed. You can also contact our duty planner, or read more about where a resource consent may be required below and avoid any potential delays to your project.