Top processing RFI’s
|
Retaining walls
|
Your retaining walls are located adjacent to an area where groups of people can gather or where individuals can approach the main access for the building. Please supply a safety barrier detail to prevent safety from falling.
|
Detail a suitable barrier complying with F4 where a fall of 1m or greater can occur.
|
|
Clarify the means of disposing the retaining wall drainage to a suitable outfall, if draining to the council storm water system this must discharge via a sump for silt removal.
|
|
|
The site plans detail the retaining wall on the boundary. Please demonstrate that all construction of the retaining wall including the excavation is within the boundary
|
Show cross section for site cut and retaining wall installation with location of boundary line to show all works contained in the site’s boundary including the cut.
|
|
Plans detail the drains running across the front of the retaining wall, the integrity of the retaining wall could be compromised.
|
Review the drainage plan. Does it need to run across the front of the retaining wall? Can the drainage be run a different way? If not, let the engineer know and the retaining wall design can take the location of the drains in to account.
|
E1
|
Surface water
|
Please describe how other property will be protected from waterborne silt runoff or transfer of sediment from the site by vehicles. To demonstrate compliance with NZBC E1.2
|
Supply sediment control plan.
|
|
Please show overland flow direction to an approved outfall for the storm water surface water, to demonstrate compliance with NZBC E1.
|
Clearly detail overland flow paths.
|
Outdoor shower
|
The building consent application requires the inclusion of; Construction details with a cross section of the outdoor shower to confirm the shower will not let other surface water surrounding the catchment area enter the council sanitary sewer system.
|
|
E2: Weathertightness
|
|
Plans and specifications do not demonstrate compliance with performances of building code clause E2 - external moisture. Where E2/AS1 is being used.
|
E2 - MBIE guidance has useful guidance material on weathertightness. Wind zones and other environmental land features can be checked on the BRANZ MAP website.
|
Roof
|
Provide project-specific flashing detail for the gutter to wall junction detail.
|
|
|
Provide project-specific flashing detail for the Barge to wall junction detail.
|
|
|
Provide chimney cap flashing detail showing overlap/upstand dimensions to comply NZBC E2.
|
|
|
Provide product appraisal and manufacturer's specification for the proposed sky-light.
|
|
|
Clarify roof fixings required for the long run roof that exceeds 12m to comply with table 16 of E2/AS1.
|
|
|
Detail the roof cladding profile to confirm the profile is suitable for proposed roof pitch.
|
|
|
Detail the roof flashing overlaps required for the roof cladding type and wind zone to confirm compliance with NZBC E2/AS1 table 7.
|
|
|
Detail the location of the roof penetration on the roof plan to demonstrate compliance with NZBC E2. For catchment areas above the penetration.
|
|
|
Detail the required valley tray width for the wind zone specified.
|
See E2/AS1 or roofing code of practice for guidance.
|
|
Detail the spreader for the down pipe discharging to the lower roof to demonstrate compliance with NZBC E2/AS1 8.1.6.
|
Show the location of the spreader on the roof plan, see E2/AS1 8.1.6 k), l) and m).
|
|
Spreader discharging on to a lower roof, catchment area over 25m².
|
Clearly detail catchment area on roof plan for the area servicing the downpipe to spreader.
|
|
Provide adequate detailing and evidence to demonstrate that unorthodox details and junctions comply with E2.
|
Detail the project specific flashing with dimensions and building mythology/ layering of the flashings to demonstrate compliance with E2. 3 dimensional drawings help with this.
|
Walls
|
Risk Matrix
|
Cladding risk matrix over 20
|
If the E2 score exceeds 20 it will require:
- a review of the design to reduce risk to a suitable number, or
- a peer review from a qualified building surveyor to assess that risk and provide Council with the details that are covered for that risk,
- verification for consideration of ULS (ultimate limit state),
- wind zone,
- testing of products under Façade AS/NZS4284, NZS 4211 performance of Windows,
- VM engineered design frames,
- materials used to construct the building Envelope B2,
- establishing risk, definitions of risk, the risk score as acceptable solution or alternative solution.
|
|
Confirm why the building requires a re-clad. Is there any evidence of moisture ingress?
|
Supply photos of existing build of areas being re-clad and building report.
|
|
Various cladding systems have been specified that are outside scope and limitation of respective appraisals. Verify/confirm from product manufactures they have reviewed all relevant architectural details and confirm application.
|
|
|
Provide deck to wall cladding/joinery clearance detail.
|
|
|
The proposed garage opening is 5m wide and the steel lintel specified to support brick cladding is outside scope of table 18E, E2/AS1. Provide specific engineered design (or) redesign.
|
|
|
No flashing detail supplied for apron flashing for wall to roof junction with an apron kick out flashing.
|
|
|
Supply project-specific details appropriate to cladding type.
|
|
|
Clarify insulation support preventing protrusion into drainage cavity.
|
See E2/AS1 for means of compliance.
|
|
Provide weatherproofing details for penetrations through cladding e.g. meter box etc. that show compliance with E2/AS1.
|
|
|
Detail the horizontal inter-storey cladding junction to demonstrate compliance with E2.
|
|
|
Detail the soffit to cladding junction for the soffit greater than 90° to demonstrate compliance with NZBC E2.
|
See E2/AS1 for means of compliance.
|
|
For windows and doors that are oversized:
Supply the engineered window design for the large sliding door detailed as 2.2m high by 8.6m wide as this is outside the scope or E2/AS1 9.1.10.1 and requires specific engineers design.
This will need to cover the engineer’s calculations structural fixings required and drainage and flow paths for the unit to demonstrate compliance with the performance criteria of E2, B1 and B2
|
|
Tanking
|
Detail means of sealing the control joint in the masonry retaining wall.
|
|
|
Supply tanking membrane appraisal and testing to confirm suitability for substrate and ground conditions.
|
|
|
Detail the location of the subsoil drain discharge point to approved outlet.
|
|
|
Detail the means of protecting the tanking membrane from the back fill to the wall.
|
|
|
Detail the tanking membrane to footing DPC junction.
|
|
|
Detail the tanking to finished ground level junction.
|
|
F2
|
Asbestos: building built pre 2000
|
Please supply the asbestos management plan to comply with the Asbestos Regulations 2017
|
If asbestos is noted, or expected, to be present as a part of the building work. An investigation and/or a procedure plan has to be submitted showing provisions for how the asbestos will be managed as a part of the construction process.
Helpful links:
WorkSafe Approved Code of Practice Guidance
Asbestos guidance
Notification of Licensed Asbestos Removal
Guide to removal
Working with asbestos
Asbestos Aware
Health and Safety at Work (Asbestos) Regulations 2016
Building Act 2004
Code Clause F1
Code Clause F2
|
Glazing
|
|
Balustrade glazing type not specified for type of glass balustrade to be installed
|
Glass balustrades have glazing specified that is compliant with the provisions of NZS 4223.3 and F4.3.4(c) and (d).
Supply manufacturer’s information.
|
F4
|
Fall protection
|
Supporting documentation is not provided to explain where barriers to upper floors or balconies require specific engineering design (SED).
|
Where the barrier design is SED, provide full project specific construction details along with a supporting producer statement for design (PS1).
|
|
Your retaining walls are located adjacent to an area where groups of people can gather or where individuals can approach the main access for the building. Please supply a safety barrier detail to prevent safety from falling 1m or greater.
|
|
|
Glass balustrade insufficient information supplied
|
supply the glass balustrade information and engineers PS1 and supporting calculations to demonstrate that the glass balustrade will comply with NZBC F4.3.4 Barriers shall be: (a) continuous and extend for the full extent of the hazard, (b) of appropriate height, (c) constructed with adequate rigidity, (d) of adequate strength to withstand the foreseeable impact of people and, where appropriate, the static pressure of people pressing against them, (e) be constructed to prevent people from falling through them.
|
G13
|
|
Specify the sanitary drainage system the design has been designed to.
|
Sanitary plumbing and drainage design cannot combine principles from G13/AS1 & G13/AS2 with principles from AS/NZ3500.2 in the same system. Clarify which design principles you are using.
|
|
Clarify means of accessing the sanitary drainage for inspection and maintenance.
|
Detail clearly on the site drainage plan access points.
|
|
Clarify the ventilation to the sanitary plumbing/drainage system to demonstrate compliance with specified system.
|
Take into account locations of braces and vent pipe sizes to wall framing size. Detail clearly on the plans.
|
|
Supply the specific design for the effluent disposal by an approved OSET designer, as per the requirements of the Bay of Plenty Regional council. Including the Schedule 5 form.
|
|
|
Regarding the gully traps specified for overflow relief, verify that there is adequate height difference to the lowest sanitary fixture.
|
|
|
Detailed means of access to the sanitary drain where it exits from under the foundation slab to demonstrate compliance with AS3500.
|
See AS3500 for means of compliance.
|
F7
|
Smoke alarms
|
Detail the locations of the required smoke alarms to the residential dwelling to demonstrate compliance with NZBC F7.
|
Ensure Domestic alarms are detailed.
Alarms should be located on each level of the household unit, within 3m of each sleeping space; and be audible to sleeping occupants.
- section 3.0 F7/AS1
Smoke alarms detailed within 3m of the bedrooms and at the change of level in the building, as per the requirement of NZBC F7.
|